Construction update: January 2019

After a three and a half week break over the Christmas/New Year period, the team at McNab are back on site and construction has recommenced at The Atrium Lutwyche.

After a three and a half week break over the Christmas/New Year period, the team at McNab are back on site and construction has recommenced at The Atrium Lutwyche.

While it might not look like much from the road, we’re very happy to announce that the piling is now 100% complete and excavation of the three-storey underground car park is 30% complete!

The team at McNab have also begun preparing and installing the in-ground services – water, sewerage, stormwater, electrical pipes and conduits. 

Construction Week 8

After a three and a half week break over the Christmas/New Year period, the team at McNab are back on site and construction has recommenced at The Atrium Lutwyche.

While it might not look like much from the road, we're very happy to announce that the piling is now 100% complete and excavation of the three-storey underground car park is 30% complete!

The team at McNab have also begun preparing and installing the in-ground services - water, sewerage, stormwater, electrical pipes and conduits. 

Construction Week 8